Integrated Islamic Facility
Building on the Shuhada Foundation’s overall vision to create an integrated community facility to serve the Islamic community; MH Planning secured planning permission for a 3,800 sq.m mosque, a community facility with a 5-a-side playing pitch on the roof, a primary school and ancillary facilities including a halal shop, barber shop and restaurant on a former HSE site at Warrenstown House, Blanchardstown, Dublin 15.
The project brief was to create a high-quality response to the site’s characteristics and the surrounding area, and to the religious and cultural needs of the Shuhada community. It was important that the proposed development should not be overly dominant relative to the neighbouring land uses and would not have an adverse impact on the visual amenities of the surrounding area, and that it would make a positive contribution to the architectural and cultural heritage of this part of Fingal in particular and west Dublin in general.
Acting as the Planning Lead and Project Coordinator, MH Planning provided strategic and project-specific advice and direction to both the Client and Design Team to ensure the successful delivery of the application. The MH Planning team engaged extensively with the planning authority and representatives of Fingal County Council, to ensure that the design was planning compliant.
Key issues of the development proposal included;
- Zoning – Aligning the development proposal with the site’s zoning objective;
- Design – Advising on the quantum of development relative to the size of the site;
- Layout – Recommendations on the optimum layout of the individual elements within the site to ensure the effective operation of the site and protection of local amenities;
- Traffic – Scoping the impact of the intensification of use of the site and consequent increase in traffic locally;
- Amenity – Addressing the issue of acoustic levels associated with the “call to prayer” and its potential impact on residential amenity;
- Landscape & Visual – Visual impact of development and in particular the proposed minaret (c.97m); and,
- Drainage – Surface water drainage management proposals.
Following a Notification of Grant of Permission from FCC, MH Planning responded to a number of 3rd Party Appeals and also prepared a successful 1st Party Appeal to An Bord Pleanála. The conditions appealed related to;
- Retail Uses – The omission of the halal shop and barber from FCCs Grant of Permission. Precedence and their status as ancillary to the main use of the site was successfully argued. Additionally, it was highlighted that the provision of halal to serve the Islamic community is a mandatory practice and that members of the Islamic community have specific barber requirements.
- Development Contributions – Successfully demonstrated the incorrect application of FCCs Development Contribution Scheme. In particular, the exemptions for a not-for-profit organisation had not been applied.
Result
On the 8th May 2018, An Bord Pleanála issued a Grant of Permission (Reg. Ref. PL06F.249341). In making its determination, the board considered that “the proposed development would not seriously injure the amenities of the area or of property in the vicinity or give rise to a traffic hazard” and accordingly the proposed development was deemed to be in accordance with the proper planning and sustainable development of the area.
In making its decision, the board permitted both the halal and barber shops as ancillary uses and omitted the requirement for a development contribution.